Nanobubble case studies from India
Eight pilots across lakes, sewage, industrial effluent, turf, aquaculture and hydroponics, each with its data and the scale of the trial. Open a case study to see the equipment, the method and what the data does not show.

How we work
Every figure on this site comes from the pilot report for that project. We state the scale, any co-treatments and what was not measured. Percentage changes are calculated from the tables. Results depend on the site, and we agree targets with you after a water assessment.
Our completed lake pilot at Nagar Bhavan Lake, Mira Bhayandar, is below. Our project at Rao Talao, also in Mira Bhayandar, is ongoing; its laboratory results to date are below.
All case studies
8 case studies.

Featured · WastewaterInstalled
Industrial ETP, Freudenberg NOK, Morinda
Sludge down 23.3%, coagulant down 22.8% and energy use down 26.9% in October 2026, the first full month after installation.
Industrial effluent (ETP) · Installed September 2026
Read the case study →
Featured · LakesOngoing
Rao Talao, Mira Bhayandar
6,000 m³ urban pond - turbidity 94 to 1.0 NTU
Lake rejuvenation, ongoing · Results as of November 2026
Read the case study →
Featured · AquacultureTrial
Open-pond carp pilot, Nadipar, Assam
Dissolved oxygen 3.5 to 7.6 mg/L and pond biomass about 3.5 times over 100 days. No control pond.
Aquaculture, pond pilot · 6 April to 10 July 2026 (reported as a 100-day cycle; closing water readings on day 90)
Read the case study →
Featured · AquacultureTrial
Tengra tank trial, Hajo, Assam
Day-100 survival 88% in the control against 95% and 92% in nanobubble tanks.
Aquaculture, tank trial · 15 November 2025 to 25 February 2026 (reported as a 100-day trial)
Read the case study →
Featured · LakesCompleted
Nagar Bhavan Lake (Mandali Talao), Mira Bhayandar
MBMC certified BOD down 53%, COD down 65%, TSS down 53% and a 100% increase in dissolved oxygen. Nanobubble generators with bioremediation.
Lake, completed pilot · Completion certified 12 September 2025
Read the case study →
Featured · Turf and hydroponicsTrial
Wankhede Stadium, Mumbai
Ammonia from 1.5 to below 0.5 mg/L, TDS from 750 to 550 mg/L over 33 days.
Turf irrigation water · 8 May to 10 June 2025 (33 days)
Read the case study →
Featured · Turf and hydroponicsTrial
Rucon Hydroponics
Germination 80.25% against 69.75% across four crops, faster basil seedlings and basil that came through peak summer.
Hydroponics, seedlings and microgreens · Seedling, basil and microgreens trials
Read the case study →
Featured · WastewaterTrial
Pirana sewage treatment plant, Ahmedabad (180 MLD)
COD from 145.88 to 20.84 mg/L with oxygen; E. coli below 2 MPN/100 mL with ozone. One sample, 60-minute batches.
Wastewater, bench trial · 3 to 5 December 2024 (bench-scale trial)
Read the case study →
Tell us about your water body or plant
We agree targets after a water assessment, then run a pilot before any scale-up.