Avior Aqua

Industrial ETP, Freudenberg NOK, Morinda: less sludge and fewer chemicals with nanobubbles

Two nanobubble generators went into the equalisation and MBBR tanks of an industrial effluent treatment plant in Punjab, with no civil changes. In the first full month, Freudenberg reports less sludge, lower chemical use and lower energy use.

Avior Aqua nanobubble generator installed at the effluent treatment plant in Morinda, Punjab
Nanobubble generator at the Morinda ETP, installed September 2026
Sludge
−23.3%
Coagulant
−22.8%
Caustic soda (NaOH)
−87%
Energy
−26.9%

October 2026 against baseline, as reported by Freudenberg.

Summary

Sludge down 23.3% and energy use down 26.9%: those were the October 2026 results at Freudenberg NOK's effluent treatment plant in Morinda, Punjab, the first full month with two 5 HP nanobubble generators in its equalisation and MBBR tanks. Coagulant, caustic soda, polymer and hydrochloric acid use all fell.

Client
Freudenberg NOK, Morinda, Punjab
Plant
Industrial effluent treatment plant: equalisation tank, MBBR, clarifier
Equipment
Two 5 HP nanobubble generators with a PSA oxygen concentrator
Installed
September 2026
Results period
October 2026 average against the plant's baseline
Source of figures
Freudenberg's project report, 4 November 2026

What was installed

Two nanobubble generators, 5 HP each, were installed on 17 September 2026. A PSA oxygen concentrator, part of the nanobubble system, was added on 20 September 2026.

One unit in the equalisation tank keeps the effluent aerobic before biological treatment. One unit in the MBBR tank supplies dissolved oxygen through the media zone. No civil changes were made.

Avior Aqua nanobubble generator with control panel and gauges
Nanobubble generator, 5 HP

What changed, as reported by Freudenberg

Results reported by Freudenberg for October 2026, the first full month after installation, against the plant's baseline.

Chemical, sludge and energy use, before and after
MeasureBefore (baseline)After (October 2026 average)Change
Sludge generation150 kg/day115 kg/day−23.3%
Coagulant14 kg/day10.81 kg/day−22.8%
Caustic soda (NaOH)2.6 kg/day0.32 kg/day−87%
Polymer0.50 kg/day0.28 kg/day−44%
Hydrochloric acid5 kg/day4.42 kg/day−11.5%
Energy260 kWh/day190 kWh/day−26.9%

Caustic soda (NaOH) dosing stopped in October 2026 apart from a single dose on 7 October, which is why the monthly average is not zero.

On site

Process diagram

Simplified process diagram Effluent flows from the inlet to the equalisation tank, then to the MBBR tank and the clarifier, and leaves as treated effluent for discharge or reuse. Settled sludge from the clarifier goes to sludge handling. A 5 HP nanobubble generator feeds the equalisation tank and another feeds the MBBR tank. A PSA oxygen concentrator supplies gas to both generators. Effluent inletEqualisation tankMBBR tankClarifierTreated effluent Flow balancing, load equalisation Biological degradation, biofilm activity RODischarge or reuse 5 HP nanobubble generator 5 HP nanobubble generator PSA oxygen concentrator Settled sludge to sludge handling
Simplified process diagram

About these results

These are the first full month of results after installation. We will add later months as Freudenberg reports them.

A bioculture product listed in the project plan had not been dosed during this period.

Tell us about your site

We reply within one working day.

Tell us about your water body or plant

We agree targets after a water assessment, then run a pilot before any scale-up.

Request a site assessment